Buying a new apartment from a developer is a significant step in anyone’s life. However, many buyers find themselves dealing with a situation in which the developer is late in delivering the apartment, for months and even years. This state of affairs can cause a great deal of aggravation, unnecessary financial expenses, and uncertainty about the move to the new home. In this article, we will examine the legal consequences that can result from a delay in delivering an apartment, detail the buyers’ rights and what compensation can be demanded from the developer, and describe ways of coping with the situation in which the apartment buyer finds himself.
What Counts as a Delay in Delivering an Apartment by the Developer That Entitles the Buyer to Compensation?
The Sale Law (Apartments), 5733-1973, provides that a delay in delivering an apartment that entitles the buyer to compensation is a delay exceeding 30 days from the date agreed upon in the sale contract with the developer.
Must damage be proven in order to receive compensation?
No.
The law grants the buyer the right to receive compensation without any proof of damage.
Buyers’ rights when the developer is late in delivering the apartment – under the Sale Law (Apartments), 5733-1973.
When the developer is late in delivering the apartment, the developer is obligated to pay the buyer compensation in the amount agreed in the sale contract, or in the amount of compensation detailed below, whichever is higher:
For a delay of months 1-4 from the date agreed in the sale agreement – the rent amount will be equal to the rent for an apartment similar in size and location.
For a delay of months 5-10 from the date agreed in the sale agreement – at 125% of the rental value of an apartment similar in size and location.
For a delay of months 11 onward, from the date agreed in the sale agreement – at 150% of the rental value of an apartment similar in size and location.
Example of a compensation calculation:
If the average rent in the area where the new apartment is located is 5,000 NIS per month, then the compensation to the buyer will be:
1. For months 1-4: 5,000 NIS * 4 = 20,000 NIS.
2. For months 5-10: (5,000 NIS * 6) * 1.25 = 37,500 NIS.
3. For months 11 onward (for example, a further delay of 6 months): (5,000 NIS * 6) * 1.5 = 45,000 NIS.
4. Total for a delay of 16 months, the developer must pay the buyer: 102,500 NIS.
This means that if the developer is late for 16 months, the buyer is entitled to total compensation of 102,500 NIS.
When is the developer exempt from paying compensation?
The developer can be released from the obligation to pay compensation in certain cases, in which it can be proven that the delay was caused by circumstances beyond his control.
Reasons the developer may claim:
The buyer’s conduct – caused solely as a result of an act or omission of the buyer.
Force majeure – wars, pandemics, or natural disasters may be considered circumstances beyond the developer’s control.
Changes in legislation – changes in regulation or approvals that were required retroactively and are beyond the developer’s control.
Strikes and delays with the authorities – delays in obtaining approvals from the local authorities may constitute justification.
Section 18 of the Contracts Law (Remedies for Breach of Contract), 5731-1970 – “If the breach of the contract was the result of circumstances of which the breaching party, at the time of making the contract, did not know and had no reason to know, or which he did not foresee and had no reason to foresee, and which he could not have prevented, and performance of the contract in those circumstances is impossible or fundamentally different from what the parties agreed, the breach shall not be grounds for enforcement of the breached contract or for damages.”
However, the courts are very strict with developers who claim “external circumstances,” and require them to prove that the delay was not caused by poor management or poor planning of the project.
How can you act in case of a delay in delivery?
If the developer is late in delivering the apartment by more than 60 days, the buyers have several legal options:
1. Letter to the developer – a demand for compensation in accordance with the Sale Law
The first step is an official approach to the developer with a demand for compensation in accordance with the law. It is recommended to do so in an official letter from an attorney, which specifies the entitlement to compensation and the amount demanded.
2.Lawsuit
If the developer refuses to pay compensation, a monetary claim can be filed.
As part of the lawsuit, you can demand:
Monetary compensation for the period in which the apartment was not delivered.
Compensation for aggravation and inconvenience.
Compensation for additional expenses incurred (rent, furniture, storage of belongings, etc.).
3. Cancellation of the contract and a lawsuit for breach of agreement
In exceptional cases of very significant delay, a lawsuit can be filed demanding cancellation of the contract and a refund of the money paid, plus compensation for the damages caused.
Case law in which the court obligated the developer to pay compensation for a delay in delivering the apartment:
1. Civil Case (Jerusalem) 10505-08 – Shlomi Kombur et al. v. B. Yair Contracting Company for Construction Works Ltd. (decided September 3, 2012)
• The court obligated the developer to pay enhanced compensation for the delay in delivery in accordance with Section 5A of the Sale Law (Apartments), which provides for compensation at 1.5 times the customary rent for the first 8 months, plus 25% for the remainder of the delay period.
2. Civil Case (Nazareth) 33536-07-13 – Dina Reil v. Dor Shevach Construction and Development Ltd. (decided June 10, 2019)
• The court awarded enhanced compensation of 104,787 NIS for the delay in delivering the apartment, calculating the compensation on the basis of multiplied rent in accordance with the provisions of the Sale Law (Apartments).
3. Small Claims (Petah Tikva) 25763-07-18 – Asaf Elisha v. Yaakobi Universal Development and Investments Ltd. (decided November 1, 2018)
• The court awarded enhanced compensation of 24,919 NIS, calculated on the basis of rent of 5,000 NIS per month plus the multiplier set by law.
4. Civil Case (Netanya) 18767-06-19 – Yehuda Andre Belhassen v. Shilat TAMA 38 Ltd. (decided August 31, 2023)
• The court emphasized the entitlement to enhanced compensation at a rate of 1.5 times the rent of an apartment similar in size and location, in accordance with Section 5A of the Sale Law (Apartments).
5. Civil Case (Afula) 42436-09-17 – Israela Noa Bershshit v. M. Karsanti Development and Investments 2008 Ltd. (decided May 19, 2021)
• The court awarded enhanced compensation on the basis of monthly rent of 2,800 NIS, applying the multiplier set by the Sale Law (Apartments).
Tips for dealing with a developer who is late in delivering the apartment:
Check the contract carefully – make sure the delivery clause is well defined and that there are no problematic clauses limiting compensation.
Document all communication with the developer – save all emails, text messages, and WhatsApp messages with the developer, so that you will have evidence in case of a lawsuit.
Seek legal advice – an attorney who specializes in real estate can draft an official warning letter for you and represent you in a lawsuit against the developer.
Check whether other buyers were harmed – sometimes a group lawsuit can be filed against the developer in case of delays in the entire project.
Demand ongoing monthly compensation – do not wait for the project to end; approach the developer and demand immediate compensation for each month of delay.
Conclusions – How to Deal with a Delay in Delivering an Apartment?
A developer’s delay in delivering an apartment is a common situation in Israel, but the Sale Law gives buyers significant protection and a right to compensation for the delay. If the developer does not meet the timetable, you can approach him with a demand for compensation, and if he refuses – a legal action can be filed.
To prevent a situation of prolonged delay without compensation, it is recommended to follow the progress of construction, approach the developer in an orderly manner, and keep documentation of all communication with him. In cases of significant delay, it is worth turning to a real estate attorney who specializes in delivery delays, in order to receive professional advice and exercise your rights in the best possible way.
Attorney Galanti has experience in real estate, including experience guiding developers and experience guiding buyers of apartments from developers.
In our experience, buyers who encounter a breach by the developer are advised to retain an attorney who will accompany them through the exhausting and complex process of dealing with the developer. Unfortunately, in quite a few situations, in light of the developer’s lack of cooperation, there is no choice but to file a lawsuit against the developer in order to stand up for the buyer’s rights.
We would be happy to assist you with any question.